桩土复合路基工后沉降早期检测评价方法研究

Study on the early detection and evaluation method of post-contruction settlement of composite subgrade

作者:单浩(河海大学);洪宝宁(河海大学);刘鑫(河海大学);徐奋强(南京工程学院)

Author:Shan Hao();Hong Baoning();Liu Xin();Xu Fenqiang()

收稿日期:2019-04-05          年卷(期)页码:2020,52(4):-

期刊名称:工程科学与技术

Journal Name:Advanced Engineering Sciences

关键字:复合路基;延时持载试验;工后沉降;早期评价方法;概率统计分析;控制标准

Key words:composite subgrade; time-delay holding test; post-contruction settlement; early detection and evaluation method; probability statistical analysis; control standards

基金项目:国家自然科学基金青年基金(No.51609071)

中文摘要

通过引入桩土复合路基静载荷试验的延时持载手段,并利用概率统计分析方法,给出了一种新的工后沉降早期检测评价方法。评价参数残余沉降Sr和沉降速率Vt由延时持载试验获得;评价指标由实测数据对比借助概率统计分析方法获得。研究表明:延时持载试验在2倍承载力设计值情况下,延时48小时可使90%以上的复合路基完成垫层的桩土应力比调整,达到稳定的承载形式。延时持载试验的最大残余沉降值小于7.0mm或大于12.0mm采用对数正态分布拟合更好;大于7.0mm且小于12.0mm采用逆γ -分布拟合更好。15年工后沉降要求值为100mm、200mm和300mm时,对应的延时持载试验最大残余沉降Srmax分别为4.5mm,13.3mm和35.41mm;对应的Vt=48分别为0.021mm/h,0.046mm/h和0.055mm/h;满足的概率分别为47.61%、87.49%、96.93%。现场实例验证表明,提出的评价指标值与实际情况比较吻合,有利于工程质量的早期检测评价,及时制定补救措施。

英文摘要

A new method for the early detection and evaluation of post-construction settlement is presented by introducing the method of delayed loading test of pile-soil composite subgrade and using the method of probability statistical analysis. The residual settlement Sr and settlement rate Vt of the evaluation parameters were obtained by the delayed loading test. The evaluation index is obtained from the measured data of composite subgrade after construction by the method of probability statistical analysis. The results show that delay the load test under the condition of double bearing capacity design value, delay 48 hours can make more than 90% of the composite subgrade complete cushion of pile-soil stress ratio adjustment, can achieve the stability of the pile soil stress ratio under actual load. The maximum residual settlement of the delayed loading test follows logarithmic normal distribution when it is less than 7.0mm or greater than 12.0mm. It follows the inverse - distribution when it is greater than 7.0mm and less than 12.0mm. When the required value of post-construction settlement after 15 years is 100mm, 200mm and 300mm, the corresponding maximum residual settlement Srmax of the delayed load holding test is 4.5mm, 13.3mm and 35.41mm respectively, The corresponding Vt=48 is 0.021mm/h, 0.046mm/h and 0.055mm/h, respectively. The probability of satisfaction was 47.61%, 87.49% and 96.93%, respectively.The field example shows that the proposed evaluation index is in good agreement with the actual situation. The evaluation method is beneficial to the early evaluation of construction quality and the timely formulation of remedial measures.